Use papers after building works: where to get it in Portugal

Independent site: we are not a public authority, and this is not legal or tax advice.

After building works, the building can be used straight away once the municipality receives a responsibility statement (termo de responsabilidade) from the works director. Final drawings are added only if the project changed. It cannot be refused if the papers are complete.

Ask for a free check

Rule
RJUE article 62-A, added by Decree-Law 10/2024
Hand in to
The câmara municipal
Document 1
Responsibility statement signed by the works director (diretor de obra) or the works inspection director, saying the work is finished and follows the project
Document 2
Final drawings (telas finais), only when the project changed
Also asked
A statistics sheet (ficha de elementos estatísticos)
Use allowed
Immediately after submission
Sources
data.dre.pt/eli/dec-lei/10/2024/01/08/p/dre/pt/html
data.dre.pt/eli/port/71-A/2024/02/27/p/dre/pt/html
Checked
2026-11-05