Works start notice (building): where to get it in Portugal
Tell the mayor in writing about the start of works, giving the site, promoter, start and end dates and the contractor. For licensed works add the licence details; for exempt works, say why no prior control is needed.
- Rule
- RJUE articles 80 and 80-A, details in Portaria 71-A/2024, annex I, item 30
- Send to
- The mayor (presidente da câmara municipal)
- Content
- Site, promoter, proof of right to build, start and end dates, who carries out the works
- Licensed works
- Procedure, title and issue date
- Exempt works
- Short description and the exemption relied on (articles 6 and 6-A)
- Sources
- data.dre.pt/eli/port/71-A/2024/02/27/p/dre/pt/html
data.dre.pt/eli/dec-lei/10/2024/01/08/p/dre/pt/html - Checked
- 2026-11-05